Production Startup

Water bottling plant turnkey: stages, timelines, budget

Equipment is the smaller part of a water project by time and a significant but not the only part by money. The real schedule is determined by documents, the site and utility networks.

9 min readUpdated August 7, 2026
Drinking water filling production line

What turnkey means

Turnkey means one contractor is responsible for the result: from concept and business plan to bringing the line to design capacity and training the personnel. The customer receives a working production, not a set of machines on the site.

The key value of this approach is a single point of responsibility. When equipment, water treatment, engineering and installation are purchased from different suppliers, the interfaces between them become a no-one's-land.

Project stages

  1. 1

    Concept and financial model

    Assortment, volumes, sales channels, cost and payback calculation. 3-6 weeks.

  2. 2

    Water source and analysis

    Well or municipal supply, extended seasonal analysis. 4-12 weeks.

  3. 3

    Site

    Selection or audit of premises, evaluation of power, water and sewer capacity. 4-8 weeks.

  4. 4

    Engineering

    Process flow diagram, layout, engineering sections, equipment specification. 6-10 weeks.

  5. 5

    Manufacturing and delivery

    Equipment production, acceptance, logistics and customs clearance. 12-24 weeks.

  6. 6

    Installation and commissioning

    Installation, piping, cold and hot trials. 6-10 weeks.

  7. 7

    Certification and ramp-up

    Product registration, production control, personnel training. 4-8 weeks.

Approximate budget structure

ItemShare of budget
Filling line and packaging40-55%
Water treatment8-15%
Engineering: compressor, cooling, compressed air10-15%
Construction and installation works, floor10-20%
Logistics and customs5-10%
Commissioning, training, documentation3-7%
Water filling triblock on a production site

How timelines are shortened

Parallel tracks
Documents and the site are prepared simultaneously with equipment manufacturing, not after.
Early water analysis
Seasonal analysis is ordered in the first project week: it determines the whole scheme.
Ready layout solutions
Typical line projects shorten the engineering stage by several weeks.
Single contractor
Removes time spent coordinating interfaces between suppliers.

FAQ

How long does the whole project take?

From the first meeting to the first shipment is usually 10-18 months. Manufacturing and installing the line is the smaller part of this timeline.

Can we start small and expand?

Yes, this is a working strategy. It is important to reserve in the layout and utilities for a second line, otherwise expansion will require shop rework.

What is the typical payback?

With adequate sales — from 18 months. The figure strongly depends on the retail price in the region, logistics radius and packaging cost.

Calculation on the topic

We will calculate your line

Describe the product, packaging formats and planned volume — we will prepare a line scheme, specification and preliminary budget estimate with payback.

  • Line scheme and unit specification for your product
  • Budget range and payback period
  • Site requirements: power, water, personnel
Select a line in the configurator

Удобный канал связи

Свидетельство о госрегистрации *

Перетащите файл сюда или выберите на устройстве · PDF, JPG, PNG, до 10 МБ

Отправляя форму, соглашаетесь с обработкой персональных данных.